A certified septic designer must design the system. Test pits must
be witnessed by the Durham Building/Health Inspector; Town fee is
$100.00. Then the designed drawings must be submitted to the Town
Zoning Officer for review. The Zoning Office then forwards the completed
application along with the required $150.00 State fee to the DES
for technical review and approval. The system installation is inspected
by the NH DES prior to covering/backfill and then a Final inspection
is performed by the Durham Building/Health inspector.